|
Home DBE Program DBE Final Rule
DBE Final Rule
Prev | Index | Next
Section 26.53 What Are the Good Faith Efforts Procedures Recipients Follow in Situations Where There Are Contract Goals?
There was little disagreement about the main point of this section.
When a recipient sets a contract goal, the basic obligation of bidders
is to make good faith efforts (GFE) to meet it. They can demonstrate
these efforts in either of two ways, which are equally valid. First,
they can meet the goal, by documenting that they have obtained
commitments for enough DBE participation to meet the goal. Second, even
though they have not met the goal, they can document that they have
made good faith efforts to do so. The Department emphasizes strongly
that this requirement is an important and serious one. A refusal by a
recipient to accept valid showings of good faith is not acceptable under this rule.
Appendix A discusses in greater detail the kinds of good faith
efforts bidders are expected to make. There was a good deal of comment
concerning its contents. Non-minority contractors recited that good
faith efforts standards should be ``objective, measurable,
realistically achievable, and standardized.'' Not one of these comments
provided any examples or suggestions of what ``objective, measurable,
realistically achievable, and standardized'' standards would look like,
however. Certainly a one-size-fits-all checklist is neither desirable
nor possible. What constitutes a showing of adequate good faith efforts
in a particular procurement is an intrinsically fact-specific judgment
that recipients must make. Circumstances of procurements vary widely,
and GFE determinations must fit each individual situation as closely as
possible.
The proposed good faith efforts appendix suggested that one of the
factors recipients could take into account is the behavior of bidders
other than the apparent successful bidder. For example, if the latter
failed to meet the contract goal, but other bidders did, that could
suggest that the apparent successful bidder had not exerted sufficient
efforts to get DBE participation. Recipients who commented on this
issue favored the concept; non-DBE contractors opposed it. The final
rule's Appendix A makes clear that recipients are not to use a
``conclusive presumption'' approach, in which the apparent successful
bidder is summarily found to have failed to make good faith efforts
simply because another bidder was able to meet the goal. However, the
track record of other bidders can be a relevant factor in a GFE
determination, in more than one way. If other bidders have met the
goal, and the apparent successful bidder has not, this at least raises
the question of whether the apparent successful bidder's efforts were
adequate. It does not, by itself, prove that the apparent successful
bidder did not make a good faith effort to get DBE participation,
however. On the other hand, if the apparent successful bidder--even if
it failed to meet the goal--got as much or more DBE participation than
other bidders, then this fact would support the apparent successful
bidder's showing of GFE. The revised Appendix makes these points.
The proposed good faith efforts appendix also expanded on language
in part 23 concerning price-based decisions by prime contractors. The
existing language provides that a recipient can use, as evidence of a
bidder's failure to make good faith efforts, the recipient's rejection
of a DBE subcontractor's ``reasonable price'' offer. The SNPRM added
that a recipient could set a price differential from 1-10 percent to
evaluate bidders' efforts. If a bidder did not meet the goal and
rejected a DBE offer within the range, the recipient could view the
bidder as not making good faith efforts. This was an attempt to provide
additional, quantified, guidance to recipients on this issue.
Comment was mixed on this issue. Non-DBE prime contractors
generally opposed the price differential idea, saying that it
encouraged deviations from the traditional low bid system. It should be
noted, however, that subcontracts are typically awarded outside any
formal low bid system. Some recipients thought that it was a bad idea
to designate a range, because it would limit their discretion, while
others liked the additional definiteness of the range. Most recipients
supported the ``reasonable price'' concept in general, even if they had
their doubts about the value of a range. Some DBE organizations favored
the range approach.
Taking all the comments into consideration, the Department has
decided to retain language similar to that of part 23, without
reference to any specific range. Appendix A now provides that the fact
that some additional costs may be involved in finding and using DBEs is
not in itself sufficient reason for a bidder's failure to meet a DBE
contract goal, as long as such costs are reasonable. Along with this
emphasis on the reasonableness of the cost necessarily comes the fact
that prime contractors are not expected to bear unreasonable costs. The
availability of a good faith efforts waiver of the contract goal helps
to ensure that a prime contractor will not be in a position where it
has to accept an excessive or unreasonable bid from a DBE
subcontractor. At the same time, any burden that a non-DBE
subcontractor might face is also limited by the reasonableness of
competing bids. This approach retains flexibility for recipients while
avoiding the concerns commenters expressed about a particular range.
The SNPRM proposed that recipients would have to provide for an
administrative review of decisions that a bidder's GFE showing was
inadequate. The purpose of the provision was to ensure that recipients
did not arbitrarily dismiss bidders' attempts to show that they made
good faith efforts. The provision was meant to emphasize the
seriousness with which the Department takes the GFE requirement and to
help respond to allegations that some recipients administered the
program in a quota-like fashion. The SNPRM also asked whether such a
mechanism should be operated entirely by the recipient or whether a
committee including representatives of DBE and non-DBE contractors
should be involved.
A number of recipients, and a few contractors, opposed the idea on
the basis of concern about administrative burdens on recipients and
potential delays in the procurement process. A greater number of
commenters, largely non-DBE contractors but also including recipients
and DBEs, supported the proposal as ensuring greater fairness in the
process. A significant majority of all commenters said that the
recipient should operate the system on its own, because a committee
would make the process more cumbersome and raise conflict of interest
issues.
The Department will adopt this proposal, which should add to the
fairness of the system and make allegations of de facto quota
operations less likely. The Department intends that reconsideration be
administered by recipients. The regulation does not call for a
committee involving non-recipient personnel. The Department intends
that the process be informal and timely. The recipient could ensure
that the process be completed within a brief period (e.g., 5-10 days)
to minimize any potential delay in procurements. The bidder would have
an opportunity to meet with the reconsideration official, but a formal
hearing is not required. To ensure fairness, the reconsideration
official must be someone who did not participate in the original
decision to reject the bidder's showing. The recipient would have to
provide a written decision on reconsideration, but there would be no
provision for administrative appeals to DOT.
A point raised by several non-DBE commenters was that DBEs should
have to make good faith efforts (even when they were not acting as
prime contractors). The commenters suggested things like providing
capacity statements and documenting that they have bid on contracts.
This point is unrelated to the subject of this section, which has to do
with what efforts bidders for prime contracts have to make to show that
they have made to obtain DBE subcontractors. It is difficult to see
what purpose the additional paperwork burdens these commenters'
requests would serve.
One of the most hotly debated issues among commenters was whether
DBE firms bidding on prime contracts should have to meet goals and make
good faith efforts to employ DBE subcontractors. Under part 23, DBE
prime contractors did not have to meet goals or make good faith
efforts. The rationale for this position was that, as DBEs, 100 percent
of the work of these contractors counted toward recipients' contract
goals, which the firms automatically met.
A significant majority of commenters on this issue--particularly
non-DBE contractors but also including some recipients and a few DBEs--
argued that DBE primes should meet goals and make GFE the same as other
contractors. Failing to do so, they said, went beyond providing a level
playing field to the point of providing an unfair advantage for DBE
bidders for prime contracts. This change would also increase
opportunities for DBE subcontractors, they said. One comment suggested
requiring DBE prime contractors to meet goals or make GFE, but stressed
that work they performed with their own forces as well as work awarded
to DBE subcontractors should count toward goals.
Supporters of the current system said that many prime contracts
performed by DBEs are too small to permit subcontracting (of course,
goals need be set only on contracts with subcontracting possibilities).
Moreover, these commenters--mostly DBEs and recipients--said that there
was already inequity as between DBEs and non-DBEs, and requiring DBEs
to meet the same requirements simply maintained the inequity. There was
also some support for a third option the Department included in the
SNPRM, in which DBEs would have to meet goals and make GFE to the
extent that work they proposed to perform with their own forces was
insufficient to meet goals.
The Department believes that, in a rule aimed at providing a level
playing field for DBEs, it is appropriate to impose the same
requirements on all bidders for prime contracts. Consequently, part 26
will depart from the part 23 approach and require DBE prime contractors
to meet goals and make good faith efforts on the same basis as other
prime contractors. However, in recognition of the DBE bidders' status
as DBEs, we will permit them to count toward goals the work that they
commit to performing with their own forces, as well as the work that
they commit to be performed by DBE subcontractors. DBE bidders on prime
contracts will be expected to make the same outreach efforts as other
bidders and to document good faith efforts in situations where they do
not fully meet contract goals.
Under part 23 and the SNPRM, recipients have a choice between
handling bidder compliance with contract goals and good faith efforts
requirements as a matter of responsiveness or responsibility. Some
recipients and other contractors recounted successful experience with
one approach or the other, and suggested reasons why everyone should
follow each approach (e.g., responsiveness as a deterrent to bid-
shopping; responsibility as a more flexible and cost-effective
approach). Both approaches have their merits, and the Department
believes the best course is to maintain the existing recipient
discretion on this issue.
Some recipients use so-called ``design-build'' or ``turnkey''
contracts, in which the design and construction of an entire project is
contracted out to a master contractor. The master contractor then lets
subcontracts, which are often equivalent to the prime contracts that
the recipient would let if it were designing and building the project
directly. In a sense, the master contractor stands in the shoes of the
recipient.
On design-build contracts, the normal process for setting contract
goals does not fit the contract award process well. At the time of the
award of the master contract, neither the recipient nor the master
contractor knows in detail what the project will look like or exactly
what contracting opportunities there will be, let alone the identity of
DBEs who may subsequently be involved. In these situations, the
recipient may alter the normal process, setting a project goal to which
the master contractor commits. Later, when the master contractor is
letting subcontracts, it will set contract goals as appropriate,
standing in the shoes of the recipient. The recipient will exercise
oversight of this process.
The final issue in this section has to do with replacement of DBEs
that drop out of a contract. What actions, if any, should a prime
contractor have to take when a DBE is unable to complete a subcontract,
for whatever reason? Should it matter whether or not the DBE's
participation is needed to achieve the prime contractor's goal?
Comment on this issue came mostly from recipients, with some non-
DBE contractors and a few DBEs providing their views. A majority of the
commenters believed that replacement of a fallen-away DBE with another
DBE (or making a good faith effort toward that end) should be required
only when needed to ensure that the prime contractor continued to meet
its contract goal. Others said that, since using DBEs to which the
prime had committed at the time of award was a contractual requirement,
replacement or good faith efforts should be required regardless of the
prime's ability to meet the goal without the lost DBE's participation.
The Department believes that, in a narrowly tailored rule, it is
not appropriate to require DBE participation at a level exceeding that
needed to ensure a level playing field. Consequently, we will require a
prime contractor to replace a fallen-away DBE (or to demonstrate that
it has made good faith efforts toward that end) only to the extent
needed to ensure that the prime contractor is able to achieve the
contract goal established by the recipient for the procurement. The
Department will also retain the SNPRM provision--supported by most
commenters who mentioned it--that a prime contractor may not terminate
a DBE firm for convenience and then perform the work with its own
forces without the recipient's written consent. This provision is
intended to prevent abuse of the program by a prime contractor who
would commit to using a DBE and then bump the DBE off the project in
favor of doing the work itself.
Prev | Index | Next
|